back to "Legal References"

Inspection Panel's Report and Findings on the Qinghai Project
Executive Summary

The Qinghai Project

1. The objective of the China: Western Poverty Reduction Project is to reduce the incidence of absolute poverty in three provinces of China: the Inner Mongolia Autonomous Region ("Part A"), Gansu ("Part B") and Qinghai ("Part C"), shown on Map 1. This Report is concerned exclusively with "Part C," the Qinghai component of the Project.

2. When the Western Poverty Reduction Project was placed before the World Bank in 1997, the basic design of the Qinghai component (hereinafter referred to more simply as the Project) was already substantially developed. Located entirely in Qinghai Province, the project comprised two parts: the so called Move-out area to the east of Xining city as shown on Map 1, and the Move-in area some 450 kilometers to the west, as shown on Map 2. The Project aims to alleviate poverty by voluntarily resettling 57,775 poor farmers who currently practice high-altitude rain-fed agriculture in five counties in Hadong Prefecture and one county in Xining City Prefecture. They will be resettled into a new irrigation project in the dryland area of the Haixi Tibetan and Mongolian Autonomous Prefecture in Dulan County. Within the Move-in area, the Project proposes to renovate an existing 8 m dam, and construct a new 40 m dam at Keri. It will also build a 29 km canal from the Xiangride river to the Keri Dam and a further 56 km canal from the Dam to supply water to irrigate some 26,500 ha in Dulan county - all shown on Map 2.

Panel Asked to Conduct the Investigation

3. The Qinghai component became the subject of public controversy in late April 1999, following the publication of an article by the Tibet Information Network. In response to this article and a growing volume of external criticism, Bank Management conducted an intensive internal review of environment and social aspects of the Qinghai Project. As a result, some "refinements" or "improvements" were proposed. Negotiations with the Chinese Government were reopened and the agreed modifications were presented in a revised loan package for Board approval.

4. On June 18, 1999, the International Campaign for Tibet (ICT), a U.S. based non-governmental organization, acting on behalf of affected people who live in the Project area, submitted a Request for Inspection to the Panel. The Requesters claimed that the Tibetan and Mongolian ethnic peoples would suffer potentially irreversible harm from the Project and that this harm stemmed from Management's failure to comply with several Bank policies and operational procedures.

5. On June 24, 1999, the World Bank Board decided to proceed with the financing of the Western Poverty Reduction Project. This decision came with a caveat, however. In an unusual move, the Board agreed "that no work be done and no funds be disbursed for the $40 million Qinghai component of the project until the Board decides on the results of any review by the independent Inspection Panel."

6. On July 19, 1999, management replied to the allegations in the Request. In brief, it considered the Project in compliance with all relevant Bank policies except that of the disclosure of information. Management pointed out that a number of "refinements" had been made to the Project since public concerns had been raised in late April. Internal reviews confirmed compliance with safeguard policies, but it had nevertheless identified areas that would benefit from additional qualitative strengthening during implementation.

7. In its report to the Board on August 18, 1999, the Panel found the Request eligible (except that the Board itself had to decide the question of external representation by ICT of protect affected people) and recommended that he Executive Directors authorize an investigation. On September 9, 1999, the World Band Board of Executive Directors authorized the Panel to conduct and investigation. The Terms of Reference required that the Panel investigate whether the Bank has violated one or more of its operational polices and procedures with respect to the design and appraisal of the Project: BP 17.50 (Disclosure of Information); OD 4.01 (Environmental Assessment); OD 4.20 (Indigenous Peoples); OD 4.30 (Involuntary Resettlement); OP 4.09 (Pest Management); OP/BP 4.37 (Safety of Dams); OP/BP 12.10 (Retroactive Financing); and OP/BP 10.00 (Investment Lending - Identification to the Board Presentation).

8. The Panel was assisted by a small team of senior consultants and a set of interpreters from outside China. Between September, 1999, and January 2000, the Panel undertook a field visit of Qinghai Province and conducted interviews in Washington, D.C., Beijing, Xining and many villages in the Project area. It also examined relevant documents, including published and unpublished literature - a process that continued through the third week of April, 2000.

General Compliance

Interpretation of the Bank's Policies and Procedures

9. During the course of examining some 20 projects over the past five years, the Panel has encountered certain differences in views among staff on just how the Bank's operational policies and procedures should be applied. In this case, however, the Panel's interviews revealed an unusually and disturbingly wide range of divergent and, often, opposing views. These large differences pervade all ranks of the staff, from senior management to front-line professionals. And they apply to virtually all of the major decisions required by the policies. The implications of this for a reasonable application of the Bank's policies and procedures became a matter of serious concern to the Panel, and ought to be of concern to the Bank generally since there is no way that the policies can by applied with reasonable consistency in the face of such wide divergences of opinion.

10. For example, a number of staff members felt that the Bank's Operational Directives and other policies were simple idealized policy statements, and should be seen largely as a set of goals to be striven after. Others of equal or more senior rank disagreed with this view. They felt that this interpretation could render the policies virtually meaningless and certainly incapable of being employed as benchmarks against which to measure compliance.

11. In discussions about compliance, staff often pointed out that the policies allow for flexibility of interpretation. The decisions made on the specific matters were thus covered and in compliance. It was simply a matter of "judgement and Management's sole discretion." The Management Response itself makes several claims in this respect. Other staff argued, however, that the policies are clear enough to distinguish areas that are binding from areas where some reasonable flexibility in interpretation is called for. Read in their entirely, the Panel feels that the directives cannot possibly by taken to authorize a level of "interpretation" and "flexibility" that would permit those who must follow these directives to simply override the portions of the directives that are clearly binding.

12. Most staff at all levels agreed that, in appraising compliance, Management had an obligation to satisfy itself not only that the process and procedures mandated by the policies had been followed, but also that the world under review met professionally acceptable standards of quality. In other words, both process and quality were essential components of compliance. Some staff, however, took the opposite view that, while it might be appropriate to ensure professionally acceptable standards of quality, it is not required for compliance. This 'check-list' or 'process' approach to compliance represents a minority view but, in the Panel's judgement, it is of concern when senior persons in the project decision-chain hold it.

13. Questions about compliance were often answered with claims of "precedent." The Management Response itself cites "…past practice with … a large number of similar integrated agricultural development projects financed by the Bank in China over the last 10 years," as a reason, for example, for assigning an environmental Category "B" rather than "A." Management's past experience in a country can obviously provide the basis for a certain level of comfort that the work required by the policies will be undertaken successfully. In the Panel's view, it is an entirely different matter, however, to suggest that experience and precedent can determine what is required by the policies.

14. Interviews with some staff were punctuated by the refrain that "in China things are done differently." This is echoed in the Management Response which states that: "The level and quality of preparation and analysis for this Project were very much in line with Bank practice in applying social and environmental policies to projects in China in the Context of its political and social systems." The Panel has carefully examined the policies and has failed to find any grounds for the view that precedents in a country, or a country's "social and political systems," can in any way determine what is required by the policies.

15. Faced with these widely divergent views among the staff, the Panel was forced to revisit its views on and experience with Bank policies and compliance. In the end, it returned to the approach reflected in its earlier reports. There is indeed room for some flexibility and interpretation but, as provided in the Resolution that established the Panel, the Operational Directives (and updated OPs, BPs, GPs, etc.) are the primary source of Bank policy for purposes of assessing compliance.

The Qinghai Project in Space and Time

16. The Environmental Assessment does not distinguish between short term impacts and those that will only occur at some time in the future. This raises serious questions about the time horizons over which the Project was evaluated.

17. Moreover, in examining the Project documentation, the Panel found a high level of ambiguity, uncertainty and inconsistency in the use of the term "project area." This confusion is compounded by the fact that the documentation is poorly supported by maps. (The Panel had eventually to prepare its own set of maps; i.e. maps 1 and 2.) As a result, it appears that significant numbers of people, including members of minority nationalities, have been left out of the environmental and social assessments required by Bank policy.

18. The "project area," as interpreted in the EA and other documentation, includes neither the commercial and service centers of Xiangride, nor several of the townships surrounding it, including some Tibetan and Mongol villages visited by the Inspection Team. Similarly, the "project area" does not include several villages between Xiangride and Dulan and between Xiangride and the new towns to be created in the Irrigation site. These omissions are difficult to understand. A network of social, commercial and political interactions clearly exists in Dulan County and in Xiangride Township. Yet no assessment has been made of how these linkages and interactions will be affected, for better or worse, by a Project that will completely change the economy and demography of the County.

19. Speaking to merchants in Xiangride, the Panel found that those who were even partially informed about the project were full of expectations that would increase their trade and commerce and that it would act as a pole of attraction for further people and investment. The same is true of the townships adjacent to the Xiangride prison farm. Their interdependence is clear.

20. Tibetan and Mongol village leaders in Xiangride township, whose villages lie directly on the proposed supply-canal route to the irrigated area, told the Panel that they had neither been officially contacted nor asked about the Project. These villages will be impacted directly by the Project's physical infrastructure and indirectly by, at the very least, a doubling of their county's population.

21. Many parts of the Move-in area have been overlooked or glossed over in the EA and in other documentation of the Project. Little or no attention was paid to the environmental impacts on areas other than the proposed new irrigation areas and the Balong Soak. Compliance with OD 4.01 requires that many other areas receive detailed consideration.

22. An adequate environmental and social assessment would require a much greater consideration of the effects of the Qinghai Project on nearby townships including Xiangride and Dulan, as well as a much larger number of villages, some visited by the Inspection Team. It would require consideration of the multiplier effects of impacts caused by the construction of the new dam and reservoir, irrigation system, roads, and townships with all their infrastructure; and also the likely population increases as the nearly 60,000 resettled farmers will have growing families and will attract more migrants, merchants, teachers, medical personnel, etc.

23. In the panel's view, given the letter and intent of ODs 4.01, 4.20 and 4.30, the actual scale of the area to be impacted by the Qinghai Project, the ethnic composition of the Project's impacted populations, and the boundaries of the "project area" were far too narrowly defined by Management. As a result, the assessments fail to address many of the most significant social and environmental impacts of the Project on the Potentially affected populations, including those who are members of minority nationalities. The Panel finds that this is not in compliance with these ODs.

The Consultation and Survey Method

24. A comparison of the three populations in the Move-in area that will be involuntarily resettled by this Project with the populations that were surveyed, is vital to an understanding of the sampling procedures. The Plan lists these impacted populations as follows: (1) 63 herder households (352 persons) who use the land "under formal lease agreements with the townships;" (2) 289 herder households (2,411 persons) who pass twice yearly, with their herds, through the area proposed for transformation into irrigated farmland and townships for the resettled population; and (3) 248 households (1,237 persons) who currently farm on the area served by an existing irrigation system, which will be integrated into the Project's new irrigation systems.

25. The extent to which these involuntarily resettled groups were "consulted" through the survey method is very different. Take the second group, for example. No survey was designed for, and no survey carried out among, the estimated 289 nomadic pastoralist households (2,411 persons) in this group, whose twice-yearly passage through project site with their herds will be disrupted. That is to say, zero percent of this group was surveyed. In stark contrast, 100 percent of the 63 herder households in the first group were surveyed. Of the 248 households (1,237 persons) in the third group, who are currently farming an irrigated area in Balong township, and whose irrigation system will be expanded and integrated into the new system, 80 households or 32 percent were surveyed.

26. Thus, the largest group of persons involuntarily resettled by this Project (i.e., the pastoralists in the second group whose passage through the irrigation site with their herds will be disrupted) received the least consultation, at least as measured by the survey data. Although this group makes up 60 percent of the people and 72 percent of the households to be involuntarily resettled, none (zero percent) of this group was surveyed, using Management's own population estimates and survey data.

27. Management also failed to consider weighting the surveys by ethnicity, or to assure adequate representation in the survey sample of affected minority groups. Most striking is the fact that in the entire move-in area only three Tibetan households were included in the survey. This is in spite of the fact that the Project occurs in a Tibetan and Mongolian Autonomous region, and the physical infrastructure for the Project (its supply-canals) passes through Tibetan villages that were not included within Management's definition of the "project area."

28. Four points can be made concerning the survey in the Move-out area. First, the questionnaires are not confidential. (All four surveys required the respondent to put his or her name on the survey.) Second, from the internal evidence of the questionnaires themselves, they must have been filled out by someone other than the individual respondents. Third, the very limited source of information about the subject matter of the survey is striking; 93% of respondents indicated that they learned of the resettlement from "government propaganda." Fourth, an examination of the questions asked, and the context in which they were asked, indicates that opinions and information gathered are probably not reliable because respondents will probably think that this questionnaire could directly influence whether they get selected for the resettlement project.

29. The hazards of using the methods of consultation discussed above are even greater in the Move-in area, because here respondents are being asked, without guarantee of confidentiality, whether they would welcome the influx of settlers. The Bank must be aware that if there is even a perception of potential adverse effects that could result from a truthful statement of opposition to this Bank-financed project, then Bank staff has a responsibility to guarantee confidentiality of the respondent. This responsibility derives from OD 4.20 and from the requirements for "full and informed" consultation in OD 4.20 (esp. par. 8), 4.30, and 4.01, since full and informed consultation is impossible if those consulted even perceive that they could be adversely affected for expressing their opposition to, or honest opinions about, a Bank-financed project.

30. Though the Bank seems to have accepted these methods of consultation, the Inspection Team found that other international organizations working in the same Qinghai province did not accept them.

31. A believable guarantee of respondent confidentiality might have yielded very different results, especially in the Move-in area. The Inspection Team's short field visit, though it recorded many positive comments about the proposed Project, also yielded some disturbing and dramatic examples of what can only be described as a climate of fear, through which some individuals nevertheless managed, at great perceived risk, to express their opposition to this Project.

32. The Project Appraisal Document admits, as does the Management Response, that the consultative process "was not always smooth nor did it fulfill all best practice guidelines. At times during the social assessment process respondent confidentiality was not fully observed, and the data gathering process was less than ideal." Nonetheless, Management still concluded that "the will of the move-in host population was adequately expressed."

33. The Panel obviously did not conduct a scientific sample of opinion during its brief stay in Qinghai. Nonetheless, in the Panel's view, the expressions of opinion it heard and the incidents it witnessed indicate the need for far greater efforts to obtain public consultation under adequate conditions, before Management can be said to have met the requirements for public consultation in the Operational Directives. The mere fact that opinions expressed were so strikingly different, and especially the fact that there was a strong perception of risk from those expressing opposition to the Project during the Inspection Team's visit, indicates that methods of public consultation used for this Project have so far been inadequate.

The Consideration of Project Alternatives

34. If there is no alternative there can be no choice. The Bank's policies and procedures leave no room for doubt as to the need for a careful and systematic consideration of a number of different types of alternatives, including investment alternatives, alternative sites, alternative project designs, alternative implementation plans. The purpose of considering these alternatives is to ensure that option is supported with will achieve the project's objectives most cost effectively, while meeting the Bank's safeguard policies.

35. One of the most noticeable and significant weaknesses of the assessments is that investment and project alternatives are neither identified nor systematically compared. For all practical purposes, the Environmental Assessment avoids consideration of alternatives, both for poverty reduction in the Move-out areas and for sites in the Move-in area. From the documentation, it is not possible to deduce whether the Qinghai Project as proposed is the best way for the Bank to meet the Project's objectives or to ensure that the Bank's safeguard policies are being respected.

36. Management failed to ensure that those responsible for the EA understood their brief to include an examination of alternatives to resettlement in both the Move-out and Move-in areas. Instead, the Panel found that they understood the main purpose of their studies to be to assist the optimal resettlement of around 60,000 people from the Move-out area into the Balong-Xiangride irrigation area. The same is true of the Social Assessment. There is no systematic study of in situ alternatives to resettlement, or of alternative resettlement sites, or of alternative development plans for the national minorities affected within the Move-in area.

37. Why the Bank accepted Assessments conducted in such circumscribed and limiting manner is unclear. Whatever the reasons, the Panel finds that the Assessments do not make any meaningful analysis of realistic project alternatives as required by Bank policy.

Environmental Compliance

Environmental Screening of the Qinghai Project

38. One of the most important decisions (perhaps the most crucial) that Management must make concerning the environmental assessment of any project is the category of the assessment that will be undertaken. Under OD 4.01, this critical judgement is made in the first instance by the Task Manager (now Task Team Leader), with the concurrence of the regional environment unit. The project is assigned to Category "A," in which case a full Environment Assessment (EA) is required, or a Category "B," in which case a full EA is not required, but an environmental analysis is, or a Category "C," in which case no environmental analysis is required. An Annex E to the OD provides illustrative lists of the types of projects best classified in Categories "A," "B" and "C." Twelve types of projects are listed for "A," of which eight are found in the entire Western Poverty Reduction Project and four in the Qinghai component of the Project. The four are: dams and reservoirs, irrigation, land clearance and leveling, resettlement and all projects with potentially major impacts on people. The OD further provides that a full EA is required if a project is likely to have significant adverse impacts that may be sensitive, irreversible, and diverse. A footnote explains that impacts qualify as "sensitive" if they affect vulnerable ethnic minorities or involve involuntary resettlement.

39. This critical decision of the category of the EA is made at a very early stage in the project cycle, but the OD permits a later revision of the category as new information becomes available. Neither the OD nor the Annex provides for exceptions on the basis of past experience or precedent in the country in question, or the area of the project relative to the area of the geographic or political jurisdiction involved.

40. The initial decision to assign "B," taken on January 8, 1998, was made before the Task Team leader, or any other Bank official associated with the decision, had an opportunity to visit the Move-in area. It was also made without detailed maps and other basic information being available and, it would appear, without regard to the illustrative examples of "A" projects mentioned above. Furthermore, the assignment was made on the stated assumption that there would be no involuntary resettlement.

41. The first Bank official involved in the decision to visit the Project site was the consultant who was engaged to be responsible for the environmental impact assessment aspects of the Project. Following his visit, on March 13, 1998, he raised a number of issues with senior staff and recommended the re-classification of the Qinghai component as an "A." Senior staff responded at length, citing reasons why it should remain a "B." Management was aware of the A/B debate, but did not intervene. The Project concept Document meeting of April 14, 1998, in effect confirmed a "B."

42. The EAs for the three components of the Western Poverty Reduction Project were received prior to the December, 1998 Decision Meeting. The same Consultant who had prepared their Terms of Reference, negotiated them with the local institutes, and overseen their implementation, also reviewed the resulting assessments and advised the Task Team Leader than he approved them - in effect, recommending them for clearance. Subsequently, the documentation for the entire Western Poverty Reduction Project was presented to the East Asia Country Director and Legal Department for clearance and authorization to issue an invitation to negotiate.

43. Following completion of the negotiations during the week of April 12, external criticism of the Qinghai component of the Project erupted, starting with publication of the Tibet Information Network (TIN) article on April 27, 1999. This triggered an intensive internal review of, inter alia, the environmental classification of the Project as "B" rather than "A."

44. Management decided to ask several senior experts from the central departments to advise on classification and compliance. One of these experts informed the Panel that from the time that he first saw any documentation related to the Qinghai project, he had been convinced that he Project should have been classified an "A" on at least eight grounds. He recommended that the project be immediately reclassified as "A" as preferable to further jeopardizing the Bank's reputation by defending the category "B." Another expert agreed that the Project should have been classified as Category "A," and told the Panel that he had advised Management that it should simply acknowledge that a "well-intentioned" mistake was made. Another expert took a slightly different view. Agreeing that if the Project were to be categorized now, under OP 4.01, it would be an "A," he understood that the size of the Project was not out of line with others in the China portfolio and that its categorization as a "B" was consistent with accepted practice in the Region.

45. A senior official, also with strong credentials in the field, informed the Panel that in his view the Project was quite clearly an "A," whether under old or new rules. The Region, he felt, was in non-compliance, not with whether or not the Project was categorized (obviously, it was), but with the A/B judgement and, in late May, he so advised Senior Management. Expressing understanding with the position of colleagues who must contract their services to, and are paid in part out of, project budgets, he went on to say that "Frankly, they don't want to bite the hand that feeds them (for cross support) by taking a hardline view."

46. After reviewing the screening process, the Panel finds that management's decision to classify the project, as a "B" was not in compliance with OD 4.01. Several components of the Project fall within the illustrative list of "A" projects in Annex E, i.e., dams and reservoirs, irrigation, and resettlement. And the impacts qualify as "sensitive" since vulnerable ethnic minorities are affected and involuntary resettlement is involved.

Environmental Assessment of the Qinghai Project

47. Management adopted a very limited definition of "environment" in the Project with the result that the Assessment fails to analyze the full range of Project effects. The assessment also fails completely to place the Project in proper time frames. As noted above, the spatial boundaries of the Move-out and Move-in areas are defined narrowly, or not at all with the result that whole communities and populations, whose lives will be impacted by the project have been left out of the Environmental and Social assessments.

48. Concerning the Move-out areas the EA and other Project documentation are moot with respect to both the plans and levels of financing for improving the living conditions of those remaining behind. There is also a lack of documentation on the social and economic implications for a village of "moving out" a significant proportion of their most productive and economically active population. This voluntary resettlement could have major, long-lasting, and irreversible social impacts. Considerably more detailed analysis of the social and environmental problems of the move-out villages and of how these all will be addressed by the Project are required in order to comply with OD 4.01.

49. In May/June 1999, following the outbreak of public concern, Management tried to compensate for this by requiring a study to evaluate the environmental and social impacts of the Voluntary Settlement Implementation Plan. This study (which is to recommend measures to enhance the environmental sustainability and the living conditions of the people in the Move-out counties) is to be undertaken not later than three years after the implementation of the Plan has commenced. Undertaking an environmental and social assessment three years after the commencement of resettlement is a bit late, not only in terms of the policies, but also in terms of any elemental understanding of the purposes of such assessments. Within the social arena, this is comparable to requiring that the safety of a proposed dam should be studied within three years after it has been built!

50. As to the Move-in area, the proposed in-migration to Dulan county will more than double its population. The proposed new towns will each have populations five times as large as Xiangride, the nearest established town to the main irrigation site. This will lead to further induced development, on which OD 4.01 lays great stress. The dam, irrigation and resettlement parts of the Qinghai Project are treated as though they were to take place in a regional vacuum. The potential impact of this development on the network of social, commercial and political interactions that exists in Dulan county and Xiangride Township has not been considered. There is no indication of how these communities and their populations will be affected, for better or worse, by the Project. Without this assessment, the Bank's policy goal of enhancing Project benefits has no substance or meaning.

51. The EA and other Project documents fail to consider the appropriate mess of implanting large-scale irrigated agriculture in this Region. It does not examine its suitability or viability in comparison with the traditional forms of land use, including agropastoralism, sedentary pastoralism, semi-sedentary pastoralism (semi-nomadism), and migratory pastoralism involving the herding of sheep and other animals. There appears simply to be an assumption that irrigated agriculture is "a good thing" without consideration of alternatives and relative costs.

52. The EA is uninformative about the layout of the new towns and villages, their infrastructure, and the facilities such as water, heat and light that will be provided for the settlers. It is silent on what methods the new towns and villages will use to manage and dispose of their wastes. Similarly, the EA is virtually silent on the impacts of the emissions and wastes on the areas surrounding and downstream from the two new towns (with initial populations nearing 30,000), and villages. Contrary to OD 4.01, the Bank's Terms of Reference for the EA did not call for any such assessment.

53. The standard of maps, charts and references is inadequate. They do not provide a satisfactory record of the settlements, infrastructure and land use in the areas that will be affected by the Project. The Qinghai Project involves a total transformation of the vegetation of some of the project areas, a substantial impact on others during the construction phases, and a substantial impact on areas that are adjacent to or downstream of the construction areas. Management should therefore have required a proper vegetation survey and map. The assessment provides no description whatsoever of the vegetation in the Move-out area, and an inadequate description of the vegetation in the Move-in area. Attention had been drawn by an FAO consultant to the urgent need for a detailed soil survey and land classification in connection with the irrigation scheme, but the recommended map (at a scale of 1:10,000) had not been complete at the time of the Panel's visit.

54. The information on the biodiversity of the area is very sketchy and inadequate. It does not incorporate an assessment of the diversity encountered with regard to distribution, frequency/rarity and conservation status. While an exhaustive inventory of the biodiversity would not be expected, it would have been appropriate to search the literature and to reference studies (including lists) as these are not lacking China.

55. Extensive exploitation of oil, natural gas and minerals is carried out in parts of the Qaidam basin and test drillings have been undertaken near the Project area. No mention is made in the EA of the general economic importance of oil and minerals in the Province, or its possible effects on the Project areas, or of any drilling activities in the Region.

56. The Panel finds that the Environmental Assessment of the Qinghai Project is not in compliance with Bank policies as set out in OD 4.01.

Dam Safety, Pest Management and Natural Habitats

57. While the design and location of the proposed Keri Dam appears to be in compliance with OP/BP 4.37 and Annex B of OD 4.00, there is no reference to the seismicity of the Project area and the fact that two earthquakes of magnitude 7+ (equivalent to the 1999 Turkish (Ismit) earthquakes), occurred in Dulan County in 1937 and 1963. An assessment of the risk to the nearby Keri irrigated area should the dam fail (as a result of an earthquake) should be undertaken in the near future.

58. The use of pesticides form part of the implementation phase. No Bank funds will be used for the procurement of pesticides, as these will be provided by the borrower as counterpart funds for the Project and, as such, acquisition and use of pesticides is an integral part of the Project. No detailed comments can be made on the subject, as the exact nature of pest management proposals is not known. In the Panel's view, the lack of pest management plans is a violation of OP 4.09. However, assurances were given to the Inspection Team that an integrated pest management programme would be undertaken for the Qinghai Project.

59. The increasing pace and scale of habitat conversion in the Qinghai-Tibetan Plateau requires a broader view to be taken of the fate of the various ecosystems in the region, not just those in or adjacent to the Project area.

60. Given the scale of absolute habitat conversion in the Project area, involving 19,000 ha of land that will be irrigated, and construction developments such as the dam, canals, townships, villages and roads - all adding up to an estimated 21,444 ha - it cannot be asserted with confidence that possible critical natural habitats will not be lost. The necessary baseline information is not available in the Assessment. The Panel is therefore of the view that the Project is in contravention of the Bank's policy, OP 4.04, in regard to the significant conversion of critical natural habitats.

Social Compliance

The Qinghai Project and Indigenous Peoples

61. OD 4.20 is quite clear about Bank policy concerning the preparation of an Indigenous Peoples Development Plan. Paragraph 13 states that: "For an investment project that affects indigenous peoples, the borrower should prepare an indigenous peoples development plan that is consistent with the Bank's policy. Any project that affects indigenous peoples is expected to include components or provisions that incorporate such a plan."

62. Management acknowledges that an Indigenous Peoples Development Plan (IPDP) is required for the Qinghai Project. It asserts, however, that the Project as a whole constitutes the IPDP because a majority or of the Project's beneficiaries are minorities. This assertion hinges on an interpretation of the last sentence of the paragraph 13 quoted above; i.e., "... When the bulk of the direct project beneficiaries are indigenous people, the Bank's concerns would be addressed by the project itself and the provisions of this OD would thus apply to the project in its entirety."

63. In the Panel's view, Management's interpretation of this one sentence of paragraph 13 of OD 4.20, cannot be accepted. In the case of this Project, it is inconsistent with other parts of the OD and especially inconsistent with the objective of Bank policy towards indigenous people, which is "...to ensure that the development process fosters full respect for their dignity, human rights, and cultural uniqueness..." and to "ensure that indigenous peoples do not suffer adverse effects during the development process..., and that they receive culturally compatible social and economic benefits."

64. The Panel's conversations with villagers inside the narrow "project area," as defined by Management, uncovered a positive attitude towards the idea of separate IPDPs for each of the minorities. When the Panel visited project-affected towns near Xiangride, and Tibetan villages along the proposed supply canal for the project - all left out of the "project area" as defined by Management - it received a similarly probative response to self-standing IPDPs for each of the ethnic groups. Although the Panel's visit was short it is satisfied that some, if not all, of the ethnic minorities in the Move-in area would welcome the opportunity to participate in the development of separate IPDPs.

65. The "indigenous peoples," or national minorities, in the Move-in area, the Hui, Mongol, Tibetan, Tu and Salar, are very different from each other, in their "cultural uniqueness" as well as their "local patterns of social organization, religious beliefs, and resource use." Retroactively lumping together these very different cultures into a single one-plan-fits-all IPDP, whether that is the "project in its entirety," or a single IPDP for the whole of the Move-in area, effectively denies these very different ethnic groups, especially the numerically weakened and most vulnerable, an opportunity to participate in a process that would ensure that their minority cultural traditions are taken into account in the overall design of the project. No number of add-on indigenous-culture-boosting activities (bilingual schools, Islamic religious sites, Tibetan pharmacological centers, corridors for nomadic herders) can override the fact that the initial project design is flawed in the failure to recognize, from the outset, the cultural uniqueness of the separate ethnic minorities involved. The Panel finds that a serious attempt to prepare separate, free-standing IPDPs for each of the national minorities in the Move-out area is required to bring the Project in compliance with OD 4.20.

66. OD 4.20 also stipulates the process and procedures to be followed in developing an IPDP within the context of the Bank's "project cycle," i.e., identification, preparation, appraisal, negotiations, and presentation to the Board. After reviewing the actual processing of this project, the Panel find that Management's decisions on Indigenous Peoples during the identification, preparation and appraisal were not in compliance with the process and procedures mandated by paragraphs 16-18 of OD 4.20. The Panel finds that the Project as a whole does not constitute the IPDP required by OD 4.20, and that separate, free-standing IPDPs are required to bring the Project into compliance with OD 4.20.

Involuntary Resettlement

67. The Qinghai Project involves two types of resettlement, voluntary and involuntary, and in assessing compliance, a clear distinction must be made between the two, since OD 4.30 only applies to involuntary resettlement.

68. Management contends that nearly 58,000 migrants from the Move-out area are "voluntary" resettlers and therefore not covered by OD 4.30. In management's view, OD 4.30 applies only to the 4,000 individuals in the Move-in area considered to be "involuntarily" affected. And, in its view, an adequate Involuntary Resettlement Plan has been prepared to cover them. The elements that now make up this Plan were originally included within the Voluntary Settlement Implementation Plan (VSIP). Later, however, following the outbreak of public concern, those provisions in the VSIP relation to involuntary resettlement were revised and brought together as separate annex to the VSIP.

69. During its discussions with people in the Move-out area, the Panel was able to confirm that they felt they had a choice whether they could move or not, and most of those interviewed wanted a move to Haiti Prefecture. Although it is difficult to say whether the choice was an informed one in many instances, OD 4.30 does not give clear guidance on the quality of full and informed choice that is needed to consider a resettlement as "voluntary." The Panel thus accepts management's contention that OD 4.30 does not apply to the migrants from the Move-out area.

70. OD 4.30 applies to those people who are displaced or adversely affected by the Project. As noted repeatedly, Management's narrow definition of the boundaries of the project area resulted in many people and communities affected by the project being left out of the assessments. This appears to be true of the population of persons who will be displaced by the Project documents. In the Panel's view, the Project is not in compliance with OD 4.30.

71. Paragraph 4 of OD 4.30 requires the development of a plan that will assist involuntarily resettled persons with their move, and will provide fair compensation for their loss (whether they lose the land itself, or the use of the land, or other productive resources.) The method of compensation chosen for the herders who are to be involuntarily resettled is "land-for-land." Adequate baseline data on pastoralism, including the data on land use and inheritance that would allow a proper assessment of the compensation offered, are unfortunately lacking for this Project. Although envisaged by the OD, it appears that this work was not done. Without the results of such work, it is difficult to assess the adequacy of the compensation offered, not only for the Panel but also, in the first instance, for Management. Indeed, it is difficult to understand how the OD's policy objectives can be achieved without this information.

72. For all of the above reasons, and others discussed in the Report, the Panel finds that the Project's current Involuntary Resettlement Plan is not in compliance with the requirements of Bank policy as set out in OD 4.30.

Disclosure of Information

73. The timely disclosure of information on evolving projects is designed to provide opportunities for comment on and improvement of Bank projects. When a project is under consideration, Bank policy requires that a Project Information Document (PID) be released on it. This needs to be made available at the Bank's Infoshop at the Project Concept Document (PCD) stage. The very short PID for the Western Poverty Reduction Project bears the same date as the PCD, March 25, 1998. It makes one reference to "minorities" or "minority nationalities," saying in passing that China's current "absolute poor" comprise "largely minority nationalities." There is no mention of minorities in the Qinghai component of the Project. Rather, the beneficiaries are defined only in terms of their poverty and their precarious future in the in the absence of the Project.

74. The Bank's policy expects that this initial PID will be updated and expanded periodically as project preparation proceeds. In any event, it is required to be revised before formal project appraisal. This was not done. If changes are then made, a final version of the PID is prepared. A first revision of the PID was made available at the Bank's Infoshop on May 4, 1999, nearly four months after the Appraisal Mission of January 26, 1999.

75. Following the TIN article, the Public Information Document (PID) was revised a second time and released on June 1, 1999. The June version contained a long, 11-page annex on "Social Aspects" of the Project. This revision is the first official public document on the Project that contains a description of the Social Assessment preparation, the selection of beneficiaries, measures for land acquisition and compensation, and measures for protecting minority rights.

76. In its Response to the Request for inspection, Management agrees that there were shortcomings in the timeliness with which the required documents were sent to the Infoshop. The EA and the Involuntary Resettlement Plan were not sent to the Board of Executive Directors and the Infoshop until June, 1999. As Management admits, the Qinghai Project is not in compliance with BP 17.50. And the Panel so finds.

Investment Lending and Retroactive Financing

77. The September 9, 1999 decision of the Board of the Executive Directors asked the Panel to look into compliance by Management with the provisions of OP/BP 10.00 on "Investment Lending: Identification to Board Presentation" and OP/BP 12.10 on "Retroactive Financing."

78. The Panel is satisfied that the Project is consistent with the Articles of Agreement and the CAS and is anchored in country policy/sector analysis, as provided in OP/BP 10.00. This Report shows, however, a number of instances where the Panel feels that operational policies and procedures were not followed, casting doubt as to whether the Project, as it stands, is the best alternative to contribute to poverty reduction and sustainable economic growth, and, thus, economically justified, as required in the same policy.

79. In the Panel's view, the Project is in compliance with OP/BP 12.10 on Retroactive Financing.

back to "Legal References"