Campus Construction
Memorial Hall Baseball/Softball Complex | Port Republic Road Athletic Facility | Duke Hall Renovation | Centennial Hall (Biotech Building) | East Campus Dining Hall | East Campus Residence Hall
Performing Arts Center
Details:
- Primary use: Academic performance venues for theater, music and dance.
- Construction started: Dec. 10, 2007
- Scheduled completion: June 15, 2010
- Square footage: 175,244
- Cost per square foot: $460
- Total building cost: About $80.7 million
- Architects: Hanbury Evans Wright Vlattas Co.
- Contractor: Nielsen Builders
- Primary energy source: gas
- Building facade: Bluestone, precast concrete
Theater program space will include:
- The proscenium theater will have 450 seats
- The studio theater will have 150 seats
- The dance theater will have 200 seats
- Offices for faculty and administration
- Costume shop, computer labs, scene shops and miscellaneous support spaces
- Lobbies and ticket sales
Dance program space will include:
- A concert hall with 600 seats
- A recital hall with 200 seats
- A large ensemble practice room for a 100-piece orchestra
- Support spaces, practice room, staff and administrative offices
- Lobby and ticket sales
More information about the Performing arts center can be found at: http://www.jmu.edu/performingartscenter/
Back to the top

|
|
The Memorial Hall Baseball/Softball Complex will be the new home for the Harrisonburg Turks in addition to the JMU baseball and softball teams. Click on image to see larger size.
|
Memorial Hall Baseball/Softball Complex
Details
- Location: Memorial Hall
- Primary use: Athletics
- Start date: construction 11/25/08
- Scheduled completion date: 11/15/09
- Total square footage: NA
- Cost per square foot: NA
- Total facility cost: approximately $8.6 million
- Name of the architect/architectural firm: Clough Harbor & Associates
- Building contractor: Nielsen Builders
- Is the work on schedule? Yes
- LEED certification information: NA
- Primary energy source: electric
- Energy efficiency: per state requirements
- Building facade (i.e., bluestone, brick, etc.): brick and metal panel
- Does the new structure replace another building(s)? yes
- Any interesting or unusual features? Baseball 1200 seats, Softball 500 seats
Back to the top

|
|
The athletic fields along Port Republic Road will be built on about 85 acres. Click on the image to see a larger view.
|
Port Republic Road Athletic and Recreational Fields
Details
- Locaiton: Port Republic Road
- Primary use: athletics and recreation
- Start date: Nov. 15, 2009
- Scheduled completion date: May 29, 2011
- Total square footage: approximately 85 acres
- Total building cost: to be determined
- Name of the architect/architectural firm: Mosely Architects
- Building contractor: to be determined
- Is the work on schedule? yes
- Primary efficiency: per state regulations
- Building facade (i.e., bluestone, brick, etc.): brick and concrete masonry
- Does the new structure replace another building(s)? yes
Back to the top

|
|
Duke Hall was completed in 1967 and is home to Latimer-Shaeffer Theatre.
|
Duke Hall Renovation
Details
- Location: on campus
- Primary use: academic fine arts
- Start date: to be determined
- Scheduled completion date: to be determined
- Total square footage: 97,120
- Cost per square foot: to be determined
- Total building cost: to be determined
- Name of the architect/architectural firm: to be determined
- Building contractor: to be determined
- Is the work on schedule: yes
- LEED Certification information: target at silver
- Primary energy source: campus systems
- Energy efficiency: per state requirements
- Building facade (i.e., bluestone, brick, etc.): to be determined
- Building capacity: to be determined
- Does the new structure replace another building(s)? no
Back to the top

|
|
A new biotechnology building is planned to go north of the Physics and Chemistry Building.
|
Centennial Hall (Biotech Facility)
Details
- Location: on campus
- Primary use: academic biology and biotechnology
- Start date: to be determined
- Scheduled completion date: to be determined
- Total square footage: approximately 90,000
- Cost per square foot: to be determined
- Total building cost: to be determined
- Name of the architect/architectural firm: Einhorn Yaffe Prescott Architects
- Building contractor: to be determined
- Is the work on schedule? yes
- LEED certification information: target at silver
- Primary energy source: campus systems
- Energy efficiency: per state requirements
- Building facade (i.e., bluestone, brick, etc.) masonry and precast concrete
- Building compacity: to be determined
- Does the new structure replace another building(s)? yes
Back to the top

|
|
Construction on the East Campus Dining Hall is scheduled to be completed in the summer of 2009 and will open for the fall 2009 semester.
|
East Campus Dining Hall
Details
- Location: on campus
- Primary use: student dining
- Start date construction 5/05/08
- Scheduled completion date: 07/08/09
- Total square footage: 50,000
- Cost per square foot: $376
- Total building cost: approximately $18.8 million
- Name of the architect/architectural firm: Mosely Architects
- Building contractor: Donly Inc.
- Is the work on schedule? yes
- LEED certification information: target at silver
- Primary energy source: campus systems
- Engery efficiency: per state requirements
- Building facade (i.e., bluestone, brick, etc.): masonry and precast concrete
- Building capacity: 800
- Does the new structure replace another building(s)? no
Back to the top

|
|
Construction of a new residence hall on the east campus started in March 2008 and is on schedule to be completed in May 2009.
|
East Campus Residence Hall
Details
- Location: on campus
- Primary use: student residence
- Start date construction 03/01/08
- Scheduled completion date: 05/01/09
- Total square footage: 132,000
- Cost per square foot: $190
- Total building cost: approximately $25 million
- Name of the architect/architectural firm: Clark Nexsen Architects
- Building contractor: Nielsen Builders
- Is the work on schedule? yes
- Reasons for any delays? NA
- LEED certification information: NA
- Primary energy source: campus systems
- Engery efficiency: per state requirements
- Building facade (i.e., bluestone, brick, etc.): masonry
- Building capacity: 422 beds
- Does the new structure replace another building(s)? No
Back to the top