Assessment of Vietnam’s National Mine Action Program

by Ted Paterson [ GICHD ] and Thao Griffiths [ VVAF ] - view pdf

A December 2012 assessment conducted by the Geneva International Centre for Humanitarian Demining and the Vietnam Veterans of America Foundation found that despite Vietnam’s well-received mine action program reform efforts, various factors, including economic and bureaucratic challenges, continue hindering progress.

Table 1. VNMAP’s funding channels.
Table 1. VNMAP’s funding channels.
All graphics courtesy of the authors.

Vietnam suffers from extensive landmine and explosive remnants of war (ERW) contamination as a result of the Vietnam War (1965–1973).1 Vietnamese officials maintain that ERW contamination covers one-fifth of Vietnams total land area, or 66,000 sq km (25,483 sq mi), and that an estimated 350,000–600,000 tons of ERW still need to be cleared.2

Vietnams response to contamination has undergone a number of distinct stages:

Figure 1. Annual expenditures for survey and clearance operations.
Figure 1. Annual expenditures for survey and clearance operations.

Financing Mine Action

VNMAP (also known as Program 504 in Vietnam as it was established in Decree 504 by the Prime Minister in December 2010) is funded primarily by its national budget and private investors, through four channels—the MoD, other ministries, subnational governments and private investors—as depicted in Table 1.3 A number of international mine action nongovernmental organizations (NGO) are active in Vietnam and generally work with provincial governments. International donors fund these NGOs. Grants from international donors such as Australia, Germany, Ireland, Norway, Taiwan, the U.K. and the U.S. averaged about US$6.1 million per annum in recent years and continue to rise.

Still, the bulk of funding comes from Vietnams national budget. Engineering Command—Vietnams headquarters for military engineering units, including demining units—reports that demining expenditures averaged US$20 million from 1979 to 2006, then rose significantly from 2006 to 2010, driven largely by a demand for demining support to infrastructure projects and private investments.4 The recession in 2011 led to a reduction in public and private investment, delaying implementation for a number of approved demining tasks.

VNMAP’s financing pattern is distinctly different from that in most other mine/ERW-affected countries (Figures 2, 3 and Table 2).

Figure 2. Areas cleared by year in Vietnam.
Figure 2. Areas cleared by year in Vietnam.

Outline of Recent Reforms

Figure 3. Financing VNMAP in Vietnam (2009).
Figure 3. Financing VNMAP in Vietnam (2009).
Figure 4. Financing mine action in other countries.3
Figure 4. Financing mine action in other countries.3

Evidence from the Vietnam Landmine Impact Survey (VLIS), as well as the World Bank and Asian Development Bank, suggests that VNMAP is effective in terms of development (e.g., support to public and private investment projects).5 However, the national program was not as effective in supporting humanitarian mine action for bottom-up initiatives of communities or for targeting clearance and mine risk education (MRE) services based on casualties incurred.

In addition, Vietnam was unable to attract international mine action support, in part because many donors refuse to finance activities undertaken by the MoD. Therefore, VBMAC initiated the reform with a demining capacity under MoLISA. VBMAC received some international funding, but this has been sporadic.

In 2010 the government approved an ambitious National Mine Action Program Plan for 2010–2025, with seven tasks set for the period of 2010 to 2015:

In 2011, the government established and appointed members to a steering committee to oversee the VNMAP plan. The plan for 2010–2015 was extremely ambitious; financing requirements reached $110 million in 2011 and continue to rise in subsequent years to an annual average of almost $150 million. Implementation was successful on some components, such as VLIS, but progress was uneven overall. In some cases, the international community seemingly remained largely unaware of new initiatives launched by VNMAP.


In June 2012 Vietnamese mine action officials requested that the Geneva International Centre for Humanitarian Demining (GICHD) undertake an assessment of VNMAP. The results were reported in December 2012 at the Vietnam Mine Action Forum held 14 December 2012 in Hanoi. The assessment focused specifically on the views of international stakeholders.

Table 2. Annual financing requirements for VNMAP 2011–2015.
Table 2. Annual financing requirements for VNMAP 2011–2015.

Working with the Vietnam Veterans of America Foundation (VVAF), GICHD developed a simple questionnaire and distributed it primarily through email to donors, U.N. agencies, operators, government ministries and provincial authorities involved in mine action. Then, on a trip to the cities of Hanoi, Quang Tri and Hue in October 2012, an assessment team from VVAF and GICHD met with 19 organizations to review responses and ask follow-up questions.

The assessment team obtained 21 questionnaire responses which were broken down into the following categories:


In brief, the assessment found that international stakeholders approved of VNMAP, but current progress disappointed them. More specifically, the majority of respondents were happy with VBMACs establishment in 2008 and with the announcement of a national program in 2010 for a variety of reasons, as these actions showed the following:

Though the national program represented a significant advance, several flaws were noted, including the following:

Most international stakeholders were unhappy with the rate of implementation for one or more components of the 2010–2015 plan. Specific concerns included the following:

International stakeholders favorably mentioned a number of recent actions, including the attendance of VBMAC officials at Mine Action Working Group meetings and the meeting of the first Vietnam Mine Action Forum in December 2011.

Figure 5. Annual financing requirements for VNMAP 2011–2015.
Figure 5. Annual financing requirements for VNMAP 2011–2015.

Interestingly, most international stakeholders seemed unaware of progress on certain fronts. For example, they were not aware of MRE messages broadcast on television in Vietnam. Nor did they know that highly contaminated provinces received national budget transfers of approximately $7.5 million per year in 2011 and 2012 for demining projects.

Concerns raised most often were the continuing dependence of VBMAC on the MoD, VBMACs lack of progress in drafting national standards, establishment of a true mine action center and the absence of a national database center.

Operators emphasized that they worked closely with provincial authorities and were not fully aware of developments in Hanoi. Most said relations with provincial authorities were improving steadily; a few expressed concern that the new national program might create problems for operators because of additional registration requirements.

International respondents presented a number of hypotheses as to why implementation lagged:

National Stakeholders

National stakeholders focused more on the work that has been done to get VNMAP operating, and mentioned the following:

The Ministry of Planning and Investment also emphasized that mine action is a priority for both official development assistance and in its priorities issued to donors. Ministry officials also spoke of plans for 2013 that awaited Prime Minister Nguyen Tan Dungs approval. These include the following:

Assuming approval is obtained, these plans address the majority of the concerns raised by stakeholders.


While VNMAPs approval was widely welcomed, the pace of implementation disappointed many stakeholders. The division of roles and responsibilities among MoD, VBMAC and the proposed regulatory office remains unclear to most stakeholders, and this represents a significant concern to those involved. Contributing to disappointing progress on other measures envisaged, the delay in providing adequate human and financial resources to the mine action center is a core problem. However, better progress can be expected in 2013 and beyond, assuming that the plans and budgets already prepared are approved. c



Ted PatersonTed Paterson has a background in international development, working with nongovernmental organizations, research and education institutes, and consulting firms, as well as in an independent consultant capacity. Paterson has been active in mine action since 1999 and has worked on socioeconomic and performance-management issues. Paterson joined the Geneva Centre for International Humanitarian Demining in 2004 and serves as senior advisor on strategic management. He has a Bachelor of Commerce from the University of Manitoba (Canada), a Master of Arts in economics from York University (Canada) and a Master of Science in development economics from the University of Oxford (U.K.).

Thao GriffithsThao Griffiths has been the country director of Vietnam Veterans of America Foundations (VVAF) Vietnam office since 2007. Previously, Griffiths worked as the senior Vietnamese program officer at VVAF and also held positions at Microsoft and the United Nations Development Programme. Griffiths holds a Master of Arts in international relations from American University (U.S.) and a Master of Science in systems engineering from Royal Melbourne Institute of Technology (Australia).


Contact Information

Ted Paterson
Senior Advisor, Strategic Management
Geneva International Centre
for Humanitarian Demining
7bis, avenue de la Paix
P.O. Box 1300
1211 Geneva 1 / Switzerland
Tel: +41 22 906 1667
Skype: gichd.t.paterson

Thao Griffiths
Vietnam Country Director
Vietnam Veterans of America Foundation (under the International Center)
No 20, Ha Hoi St
Hanoi / Vietnam
Tel: +84 4 733 9444
Skype: thaogriffiths



  1. In Vietnam, this war is called the American War.
  2. “Mine Action in Vietnam and GICHD Support.” GICHD.
    . Accessed 1 May 2013.
  3. “Vietnam.” Landmine and Cluster Munition Monitor.
    . Accessed 29 March 2013.
  4. Interview with Deputy Commander of Engineering Command, Sr. Col. Tuan, 5 October 2012.
  5. “Vietnam Unexploded Ordnance and Landmine Impact Assessment & Rapid Technical Response in Six Provinces of Nghe An, Ha Tinh, Quang Binh, Quang Tri, Thua Thien Hue and Quang Ngai.” Vietnam Veterans of America Foundation, Hanoi, 2009. docs/
    . Accessed 13 May 2013.